US 90A (from I-10 to SR 297) [218605-7]

US 90A (from I-10 to SR 297 / Pine Forest Road) / FDOT FPID 218605-7 / #NW78 / Perdido River and Bay Watershed / Escambia County

Road improvements to US 90A (from I-10 to SR 297) resulted in direct impacts to an estimated 1.00 acres of jurisdictional wetlands.  This impact is not within the service area of any private mitigation bank.  Mitigation consisted of debiting palustrine forested credits at the Dutex ILF Mitigation Area.

SAJ-2016-03316 RGP-RLT (1/22/2017)

USACE Permit Attachments (14 MB)

FDEP-0345798-003-EI (1/18/2017)

FDEP Permit Attachments (59 MB)

ILF Federal Debit Request Letter (5/4/2017)

Note: Road segments FPID 218605-6 (US 90 from CR 99 to I-10) and FPID 218606-7 (US 90A from I-10 to SR 297) were permitted together by both the USACE and FDEP.  Per permit conditions, 1.96 federal / 1.51 state credits have been debited from the Dutex credit ledger as combined mitigation for segments 218605-6 and 218605-7.